Skip to main content

Ground-up
construction.

Ground-up construction is the cleanest version of the work — a vacant or fully demolished parcel, a complete code-compliance path from feasibility through Certificate of Occupancy, and a building that owes nothing to a previous structure. The path is longer than a remodel but more predictable when the lot has been diligenced upfront. We start with a feasibility memo on your parcel before any drawings start.

CA Lic. #1145233

On a vacant lot the question is not 'can we build it' — it is 'what is the highest-and-best-use the zoning + utilities + geotech actually support?' Answer that first, design second.

What we mean by ground-up construction.

  • G-01 · Vacant-lot single-family

    Size
    1,800 – 4,200 sqft
    All-in
    $450 – $850 / sqft
    Schedule
    10 – 16 months build

    Most common ground-up scope. Foundation strategy comes out of geotech; framing and dry-in usually run 10–16 weeks.

  • G-02 · Vacant-lot duplex / triplex

    Size
    1,400 – 2,200 sqft per unit
    All-in
    $420 – $750 / sqft
    Schedule
    12 – 18 months build

    R2 / R3 zoning or SB 9 split. Each unit gets independent utilities, fire-rated separation per CBC §420, and NFPA 13D residential sprinklers depending on geometry.

  • G-03 · Vacant-lot fourplex

    Size
    1,200 – 1,800 sqft per unit
    All-in
    $400 – $700 / sqft
    Schedule
    14 – 20 months build

    Type V residential. Accessibility, fire-rated assemblies, and EVCS readiness extend plan check vs. SFR.

  • G-04 · Vacant-lot small multifamily (5–10 units)

    Size
    Site-dependent
    All-in
    $380 – $650 / sqft
    Schedule
    16 – 24 months build

    Type V on slab or Type V over Type I podium. SB 423 ministerial review can shorten entitlement on qualifying parcels.

  • G-05 · Tear-down then ground-up

    Size
    Replaces existing footprint
    All-in
    $500 – $1,000 / sqft + demo
    Schedule
    14 – 22 months total

    Demolition with asbestos and lead-paint surveys (homes built before 1981), SCAQMD Rule 1403 notification, then a clean ground-up build.

Real California cost ranges.

All-in 2026 ground-up costs in the LA basin and Bay Area run $400–$850/sqft for flat-lot single-family and small multifamily, with hillside and coastal parcels reaching $850–$1,400/sqft. Soft costs (architecture + structural + Title 24 + permits + geotech) are typically 12–18% of hard-cost subtotal. Bay Area runs at the top of every band.

  • Site work + grading

    Flat lot: $40k–$120k. Hillside or hillside with retaining: $150k–$400k+. Coastal bluff: $200k–$600k+.

  • Foundation

    Slab-on-grade $25–$45/sqft. Pier + grade-beam $50–$90/sqft. Caissons $80–$160/sqft in hillside or fault-zone soils.

  • Structural framing

    Wood frame on flat lot $60–$110/sqft. Steel moment frame or specialty shear walls add $15–$40/sqft.

  • Title 24 + CALGreen

    Heat pumps, high-performance envelope, solar PV, battery readiness — $35–$70/sqft above 2019-code construction.

  • Utility upgrades

    200A/400A electrical service $4k–$18k. New sewer lateral $8k–$28k. New water service $6k–$22k. Gas service $4k–$12k.

  • Soft costs + permits

    Architecture + structural + Title 24 + permits + geotech: 12–18% of hard-cost subtotal.

The permit path.

Ground-up builds are permitted as new construction at the local building department. Plan-check turnaround varies sharply by jurisdiction — LADBS, SF DBI, and Oakland all sit at the long end (16–32 weeks with corrections). Smaller suburban departments often clear in 8–16 weeks. Get the jurisdictional window confirmed before you sign a closing date.

  • Building permit (architectural + structural)
  • Mechanical, electrical, plumbing permits
  • Title 24 energy compliance per CEC 2022 code
  • CALGreen worksheet (residential mandatory measures)
  • Grading permit when cut/fill exceeds 50 cubic yards
  • Sewer and water service permits (utility provider)
  • Demolition permit with asbestos + lead survey (CCR Title 8 / SCAQMD Rule 1403) if tearing down
  • Coastal Development Permit, Hillside Compliance Review, or WUI assembly review as applicable

How California code shapes the work.

California ground-up construction is designed against CEC 2022 Title 24, CALGreen, and the locally-adopted California Residential Code amendments. Hillside, fault-rupture, liquefaction, methane, and VHFHSZ overlays each add their own reports, assemblies, and review tracks at plan check.

What the schedule actually looks like.

  1. Step 01

    Feasibility memo

    Zoning envelope, FAR, utilities, geotech risk, plan-check window.

    2 – 4 weeks
  2. Step 02

    Schematic + DD

    Massing, structural strategy, Title 24 model.

    10 – 16 weeks
  3. Step 03

    Construction documents

    Permit-set drawings, Title 24, CALGreen, civil, MEP.

    8 – 14 weeks
  4. Step 04

    Plan check + permit

    Tighter in suburban departments; longer in LADBS, SF DBI, Oakland.

    8 – 32 weeks
  5. Step 05

    Demo + sitework

    Demo (if any), grading, rough utilities, foundation prep.

    4 – 12 weeks
  6. Step 06

    Foundation → framing → dry-in

    Foundation pour through weather-tight envelope.

    14 – 24 weeks
  7. Step 07

    MEP + finishes

    Rough, insulation, drywall, cabinetry, flooring, trim.

    18 – 30 weeks
  8. Step 08

    Commissioning + CofO

    HVAC start-up, solar interconnection, finals, CofO.

    4 – 8 weeks

How we run this work.

Every ground-up engagement starts with a feasibility memo — written, sourced, and parcel-specific. That document covers zoning envelope, geotech scoping, utility capacity, overlay exposure (hillside, coastal, WUI), and a realistic plan-check window for the jurisdiction.

Design and engineering proceed in three reviews and lock at construction documents. We do not put schematic drawings out for bid; doing so produces numbers that fall apart in plan check and erodes owner trust.

Construction runs on a design-build contract with named subcontractors, weekly schedule updates, monthly budget reconciliation, and a published RFI / change-order protocol. Inspection logs are available on demand.

Frequently asked.

What is 'ground-up construction'?
Building from a vacant lot or a fully-demolished lot up to a completed structure, fully permitted as new construction. It is distinct from major remodels, which retain the existing foundation and a substantial portion of the structural envelope.
How long does a ground-up build take?
For a flat lot in a moderate jurisdiction: 6–10 months pre-construction and plan check, then 10–16 months of construction. About 16–26 months total. Hillside, coastal, or WUI parcels add 4–10 months because of additional reviews and assemblies.
Do I need a geotechnical (soils) report?
For practical purposes, yes. California Building Code Chapter 18 lets the building official require a geotechnical investigation for any new foundation, and in LA County hillside zones, fault-rupture zones, liquefaction zones, methane zones, and most coastal soils, a soils report is required, not optional.
Can I keep some of the existing structure to save cost?
Sometimes — keeping 50%+ of the existing exterior walls can let you permit as a major remodel in some jurisdictions, which is cheaper at plan check. The trade-off is that you inherit the existing foundation and seismic risk. We model both options before you commit.
How much does ground-up construction cost per square foot?
All-in 2026: $400–$700/sqft for production-grade SFR in moderate jurisdictions, $550–$850/sqft for semi-custom on flat lots, and $850–$1,400/sqft for hillside or coastal custom. Bay Area sits at the top of every band.
What happens if my lot has a fault-rupture or liquefaction overlay?
The geotechnical report drives foundation strategy — usually pier-and-grade-beam or drilled caissons — and the structural engineer designs to those conditions. Plan check requires the geotech report on file before structural review starts.
Will solar be required?
Yes for almost all low-rise residential under CEC 2022 Title 24. The code requires solar PV sized to projected annual electrical load with limited exemptions. Battery storage readiness is also required for several climate zones.

Start with a feasibility memo.

Tell us about the parcel and the program. We'll come back with a written feasibility memo before any design work starts.

request a quote

Tell us what you’re building.

A few specifics — city, scope, budget, target date. We’ll come back with a one-page feasibility note within the week.

Phone or email — at least one so we can reply.

We use this to route your lead to the right studio. No spam, ever.

Trade cardLeo's on site · replies in ~3h

Want a real number for your Ground Up Construction job?

  • We open the books on similar jobs from the last 24 months
  • Hand-built estimate, not a software auto-quote
  • Includes permits, finishes, and the boring stuff

3-day turnaround · Free

Compare scopes

Contact form · 30 seconds

or call (818) 650-3197

No spam. We reply personally — usually within 3 hours.

Call