How long an ADU really takes in San Gabriel Valley

Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.

Stage by stage

Survey + design
3–5 — Most SGV lots are flat — minimal site work.
Landmark District review
4–8 — Skip if not in a designated district.
City plan check
4–6 — Pasadena / Glendale / Burbank counters are quick.
Construction
16–22 — Detached new-build, slab to final.

Permit clock vs total schedule

Ministerial permit
6–10 weeks
Discretionary review (when triggered)
12–20 weeks

What slips schedules in this area

  • Pasadena, Glendale, and Burbank each run their own building & safety — generally faster than LADBS.
  • Pasadena has 11 designated Landmark Districts — design review applies on contributing structures.
  • Burbank Water & Power and Glendale Water & Power are separate from LADWP — different fees and timelines.
quote · san gabriel valley

Quote for San Gabriel Valley timeline.

When are you trying to break ground? We'll lay out a realistic week-by-week schedule for your jurisdiction.

Phone or email — at least one so we can reply.

We tag this lead as la-sgv · timeline so the right estimator picks it up. First site walk is free.

Call