How long an ADU really takes in San Fernando Valley

Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.

Stage by stage

Survey + design
2–4 — Standard R1 lots only need a basic ALTA.
LADBS plan check
4–6 — Online portal, ministerial.
Permit + utility coordination
1–2 — LADWP service drop scheduling.
Construction
14–20 — Detached new-build on flat lot.

Permit clock vs total schedule

Ministerial permit
6–10 weeks
Discretionary review (when triggered)
14–20 weeks

What slips schedules in this area

  • Mostly flat R1 — ideal for detached new-build ADUs up to 1,200 sqft.
  • Mulholland Scenic Parkway parcels add a Specific Plan review along the ridgeline.
  • Very High Fire Hazard Severity Zone (VHFHSZ) on the south side → Chapter 7A exterior assemblies.
quote · san fernando valley

Quote for San Fernando Valley timeline.

When are you trying to break ground? We'll lay out a realistic week-by-week schedule for your jurisdiction.

Phone or email — at least one so we can reply.

We tag this lead as la-valley · timeline so the right estimator picks it up. First site walk is free.

Call