Eastside / NELA · Timeline
How long an ADU really takes in Eastside / NELA
Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.
Stage by stage
- Survey + slope analysis
- 3–5 — Hillside lots need a topo + soils report early.
- OHR review (HPOZ only)
- 4–8 — Skip if outside an HPOZ.
- LADBS plan check
- 5–7 — Ministerial; longer on hillside grading sheets.
- Construction
- 18–26 — Hillside adds retaining + haul-route days.
Permit clock vs total schedule
- Ministerial permit
- 8–12 weeks
- Discretionary review (when triggered)
- 14–22 weeks
What slips schedules in this area
- HPOZs (Highland Park, Angelino Heights, Adams-Normandie) require Office of Historic Resources review.
- Hillside Construction Regulation overlays in Silver Lake / Echo Park drive haul-route permits.
- Many lots have legal-but-undocumented in-law units; we map them before drawing.