How much an ADU actually costs in California (2026).

Detached new-build ADUs run $250–$385/sqft in LA and $310–$485/sqft in the Bay. Garage conversions and JADUs come in lower — but only when the existing shell passes inspection.

Installed cost bands

$/sqft of finished area for these scopes — LA versus Bay Area, side by side.

ScopeLos AngelesBay Area
Detached new-build ADU
$250–$385
Driven by foundation type, site access, finish tier.
$310–$485
Bay labor premium; hillside lots push the high end.
Attached ADU / addition
$220–$340
Tie-in to existing structure adds soft cost.
$285–$430
Roof and shear-wall integration are budget drivers.
Garage conversion ADU
$145–$230
Only pencils if slab + walls are sound.
$180–$290
Older garages often need full slab tear-out.
JADU (within main house)
$125–$195
Lowest entry point — limited to 500 sqft.
$160–$245
Plumbing fixture relocation is the swing item.

What drives the spread

  1. 1.

    Foundation type

    A continuous footing on flat dirt is the baseline. Pier-and-grade-beam on a hillside, or a structural slab over expansive clay, can add 15–30% to the foundation line alone.

  2. 2.

    Site access + staging

    If the only path to the rear yard is a 36-inch gate, every yard of concrete and stick of lumber is hand-carried. Budget another $8–14K versus a job with truck access.

  3. 3.

    Finish tier

    Builder-grade IKEA-equivalent vs. semi-custom cabinets vs. quartz-everywhere swings $/sqft more than any other single choice. Lock the spec before you sign.

  4. 4.

    Utility upgrades

    A new ADU usually triggers a sub-panel; a 60+ year-old service often forces a 200A upgrade. Sewer lateral compliance, water meter upsize, and PG&E queues are the schedule killers.

  5. 5.

    Code cycle

    The 2025 Title 24 cycle (effective Jan 1, 2026) raised the bar on envelope U-values, balanced ventilation, and EV-ready wiring. Budget 3–6% above 2024 numbers for the same scope.

Soft costs to add on top

The hard-cost bands above exclude these. Forgetting them is the most common reason a budget runs 20% over.

Line item% of hard cost
Design + engineering (architectural, structural, Title 24)
Higher end for hillside, custom, or historic-overlay parcels.
612%
Permits + plan check (LADBS / SF DBI / etc.)
Add school fees ($4–6/sqft for ADUs > 750 sqft).
25%
Utility upgrades (panel, sewer lateral, water meter)
Pre-1980 homes routinely hit the top of this range.
38%
Survey + soils report
Required on hillside and parcels with fault-zone proximity.
0.52%
Owner contingency
Skip this and the next discovery becomes a change-order argument.
815%

Los Angeles — burdened hourly rates

Includes payroll burden + small-tool allocation. Excludes overhead & profit.

Journeyman carpenter
$62–$92/hr
Journeyman electrician
$78–$118/hr
Journeyman plumber
$82–$125/hr
General laborer
$38–$56/hr

Bay Area — burdened hourly rates

Includes payroll burden + small-tool allocation. Excludes overhead & profit.

Journeyman carpenter
$78–$118/hr
Journeyman electrician
$95–$145/hr
Journeyman plumber
$98–$150/hr
General laborer
$48–$72/hr

Field calculator

Run your scope through the ADU calculator

Inputs match the bands on this page — same data, your scope.

Open calculator →

What this is based on

  1. 1.

    California ADU statute (Gov. Code §65852.2) caps impact fees and requires ministerial review for compliant units.

    California HCD · view source

  2. 2.

    ADU Handbook (2025 update) sets the minimum allowances every jurisdiction must honor.

    California HCD · view source

  3. 3.

    2022 Energy Code requirements remain in force until the 2025 cycle takes effect Jan 1, 2026.

    California Energy Commission · view source

  4. 4.

    NAHB construction cost surveys confirm 60–65% of single-family build cost flows to labor + materials.

    National Association of Home Builders · view source