Detached new-build ADUs run $250–$385/sqft in LA and $310–$485/sqft in the Bay. Garage conversions and JADUs come in lower — but only when the existing shell passes inspection.
Installed cost bands
$/sqft of finished area for these scopes — LA versus Bay Area, side by side.
| Scope | Los Angeles | Bay Area |
|---|---|---|
| Detached new-build ADU | $250–$385 Driven by foundation type, site access, finish tier. | $310–$485 Bay labor premium; hillside lots push the high end. |
| Attached ADU / addition | $220–$340 Tie-in to existing structure adds soft cost. | $285–$430 Roof and shear-wall integration are budget drivers. |
| Garage conversion ADU | $145–$230 Only pencils if slab + walls are sound. | $180–$290 Older garages often need full slab tear-out. |
| JADU (within main house) | $125–$195 Lowest entry point — limited to 500 sqft. | $160–$245 Plumbing fixture relocation is the swing item. |
What drives the spread
1.
Foundation type
A continuous footing on flat dirt is the baseline. Pier-and-grade-beam on a hillside, or a structural slab over expansive clay, can add 15–30% to the foundation line alone.
2.
Site access + staging
If the only path to the rear yard is a 36-inch gate, every yard of concrete and stick of lumber is hand-carried. Budget another $8–14K versus a job with truck access.
3.
Finish tier
Builder-grade IKEA-equivalent vs. semi-custom cabinets vs. quartz-everywhere swings $/sqft more than any other single choice. Lock the spec before you sign.
4.
Utility upgrades
A new ADU usually triggers a sub-panel; a 60+ year-old service often forces a 200A upgrade. Sewer lateral compliance, water meter upsize, and PG&E queues are the schedule killers.
5.
Code cycle
The 2025 Title 24 cycle (effective Jan 1, 2026) raised the bar on envelope U-values, balanced ventilation, and EV-ready wiring. Budget 3–6% above 2024 numbers for the same scope.
Soft costs to add on top
The hard-cost bands above exclude these. Forgetting them is the most common reason a budget runs 20% over.
| Line item | % of hard cost |
|---|---|
| Design + engineering (architectural, structural, Title 24) Higher end for hillside, custom, or historic-overlay parcels. | 6–12% |
| Permits + plan check (LADBS / SF DBI / etc.) Add school fees ($4–6/sqft for ADUs > 750 sqft). | 2–5% |
| Utility upgrades (panel, sewer lateral, water meter) Pre-1980 homes routinely hit the top of this range. | 3–8% |
| Survey + soils report Required on hillside and parcels with fault-zone proximity. | 0.5–2% |
| Owner contingency Skip this and the next discovery becomes a change-order argument. | 8–15% |
Los Angeles — burdened hourly rates
Includes payroll burden + small-tool allocation. Excludes overhead & profit.
- Journeyman carpenter
- $62–$92/hr
- Journeyman electrician
- $78–$118/hr
- Journeyman plumber
- $82–$125/hr
- General laborer
- $38–$56/hr
Bay Area — burdened hourly rates
Includes payroll burden + small-tool allocation. Excludes overhead & profit.
- Journeyman carpenter
- $78–$118/hr
- Journeyman electrician
- $95–$145/hr
- Journeyman plumber
- $98–$150/hr
- General laborer
- $48–$72/hr
Field calculator
Run your scope through the ADU calculator
Inputs match the bands on this page — same data, your scope.
Open calculator →What this is based on
1.
California ADU statute (Gov. Code §65852.2) caps impact fees and requires ministerial review for compliant units.
California HCD · view source
2.
ADU Handbook (2025 update) sets the minimum allowances every jurisdiction must honor.
California HCD · view source
3.
2022 Energy Code requirements remain in force until the 2025 cycle takes effect Jan 1, 2026.
California Energy Commission · view source
4.
NAHB construction cost surveys confirm 60–65% of single-family build cost flows to labor + materials.
National Association of Home Builders · view source
Ready to scope it?
See our ADU Builder pillar
Process, materials, code walkthroughs, and case studies for this scope — built from the same job tracking as the numbers above.
Open service pillar →Further reading
Field journal
How to finance an ADU in California (2026): HELOC, CalHFA, refi, cash
Five financing paths for a California ADU in 2026 — including the CalHFA $40K grant, construction-to-perm loan…
Field journal
Shed, studio, JADU, or full ADU? A California buyer's framework
Four ways to add a small structure in your California backyard. Which one matches your goal — rental income, h…
Field journal
SB 9 lot splits in Los Angeles: what the law promises vs. what LA approves
SB 9 was supposed to unlock duplex + lot-split development on every R1 parcel in California. Three years in, L…