How long an ADU really takes in Inland Empire

Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.

Stage by stage

Survey + design
2–4 — Big flat lots — minimal site analysis.
City plan check
4–6 — Ministerial portals — Riverside / Corona / RC are fast.
SCE service coordination
2–8 — Often the long pole on detached new-builds.
Construction
14–18 — Flat lots, easy access — fastest construction in our region.

Permit clock vs total schedule

Ministerial permit
5–9 weeks
Discretionary review (when triggered)
12–20 weeks

What slips schedules in this area

  • Generally the most permissive corner of our service area — flat lots, big parcels, fast review.
  • VHFHSZ at the San Bernardino mountains foothills → Chapter 7A on north-facing slopes.
  • Some unincorporated parcels run through county directly — faster for ADUs, slower on inspections.
quote · inland empire

Quote for Inland Empire timeline.

When are you trying to break ground? We'll lay out a realistic week-by-week schedule for your jurisdiction.

Phone or email — at least one so we can reply.

We tag this lead as inland-empire · timeline so the right estimator picks it up. First site walk is free.

Call