ADU permits in Hills & Canyons
Typical timeline
LADBS: 12–18 weeks because of slope, geotech, and hillside ordinance.
What changes about the permit here
Hill parcels add the Baseline Hillside Ordinance, geotech, and (along the ridgeline) the Mulholland Scenic Parkway Specific Plan to every permit package. The ADU itself is still ministerial, but plan-check takes longer because the structural, grading, and haul-route sheets are heavier than a flat-lot project.
- BHO caps height to ~33 ft and limits grading cuts based on lot slope.
- Soils / geotech report required on any slope >10%.
- Hillside Construction Regulation permits gate haul-route hours and truck size.
- Beverly Hills + Bel-Air HOA / R1 design review runs parallel to building permit.
On-the-ground notes
- Baseline Hillside Ordinance caps height, grading cuts, and building footprint based on slope.
- Mulholland Scenic Parkway Specific Plan applies along the spine — separate Director's review.
- Beverly Hills parcels run their own R1 design review; Bel-Air HOAs review separately.
Go deeper on Hills & Canyons
Services in Hills & Canyons
Hills & Canyons ADU Builder
Local scope + permit →
Hills & Canyons Garage Conversion
Local scope + permit →
Hills & Canyons JADU Builder
Local scope + permit →
Hills & Canyons Kitchen Remodeling
Local scope + permit →
Hills & Canyons Bathroom Remodeling
Local scope + permit →
Hills & Canyons Home Additions
Local scope + permit →
Hills & Canyons Whole-Home Remodeling
Local scope + permit →