Hills & Canyons · Permits

Hills & Canyons ADU permits, step by step

Hill parcels add the Baseline Hillside Ordinance, geotech, and (along the ridgeline) the Mulholland Scenic Parkway Specific Plan to every permit package. The ADU itself is still ministerial, but plan-check takes longer because the structural, grading, and haul-route sheets are heavier than a flat-lot project.

What's specific to this area

  • BHO caps height to ~33 ft and limits grading cuts based on lot slope.
  • Soils / geotech report required on any slope >10%.
  • Hillside Construction Regulation permits gate haul-route hours and truck size.
  • Beverly Hills + Bel-Air HOA / R1 design review runs parallel to building permit.

On-the-ground notes

  • Baseline Hillside Ordinance caps height, grading cuts, and building footprint based on slope.
  • Mulholland Scenic Parkway Specific Plan applies along the spine — separate Director's review.
  • Beverly Hills parcels run their own R1 design review; Bel-Air HOAs review separately.

Permit clock

Ministerial (state ADU law)
12–18 weeks
Discretionary review (when triggered)
22–36 weeks
quote · hills & canyons

Quote for Hills & Canyons permits.

Tell us where you're stuck on permits and what you're trying to build. We'll line up the right permit path with the local building department.

Phone or email — at least one so we can reply.