San Fernando Valley ADU permits, step by step The Valley is the most predictable corner of LA city for an ADU permit. Standard R1 lots, flat topography, and LADBS's online portal mean state ADU law applies cleanly with no neighbor notice and no discretionary review. The two variables are the Mulholland Scenic Parkway Specific Plan (south-side hillside parcels) and Very High Fire Hazard Severity Zones.
What's specific to this area ☐ Ministerial review under LAMC §12.22-A,33 — no public hearing. ☐ Detached rear-yard ADUs fit standard 50×150 lots without variances. ☐ VHFHSZ parcels require Chapter 7A ignition-resistant exterior assemblies. ☐ Mulholland Specific Plan parcels need a separate Director's Determination before LADBS. On-the-ground notes ☐ Mostly flat R1 — ideal for detached new-build ADUs up to 1,200 sqft. ☐ Mulholland Scenic Parkway parcels add a Specific Plan review along the ridgeline. ☐ Very High Fire Hazard Severity Zone (VHFHSZ) on the south side → Chapter 7A exterior assemblies. Permit clock
Ministerial (state ADU law) 6–10 weeks
Discretionary review (when triggered) 14–20 weeks Reference
Terms and guides for this page Glossary terms LADBS (LA Department of Building and Safety) The City of Los Angeles agency that issues building permits and conducts inspections.
ePlan LADBS's fully electronic plan-check portal for residential and commercial permits.
Ministerial Review Permit review based purely on objective standards — no public hearing, no discretion.
Title 24 California's energy efficiency code — required for all new construction and most additions.
HERS Rating Field verification of energy-efficiency measures required by Title 24.
AB 68 2020 California law that streamlined ADU permits — 60-day clock, parking exemptions, ministerial review.
Field guides The Los Angeles ADU permit process, step by step Permitting an ADU inside the City of Los Angeles takes about 8–11 weeks of plan check (LADBS) plus 2–4 weeks of pre-submittal prep. State law caps ministerial review at 60 days from a complete submittal. Total city + utility fees for a 700 sqft detached ADU typically run $13,000–$26,000.
LADBS ePlan: a builder's walkthrough of the LA permit portal LADBS ePlan is the City of LA's mandatory electronic portal for residential plan check. All single-family and two-family permits since 2022 must be filed here. Typical workflow: register a project, upload PDF drawings, pay plan-check deposit, receive corrections in 2–4 weeks, resubmit through 2–3 cycles, pay final fees, download the issued permit.
Related reading
More on San Fernando Valley From the journal
Further reading permits · 10 min read
Every step of the LADBS ADU permit pipeline — pre-application, plan check, corrections, fees, and the inspections that decide your schedule.
permits · 8 min read
What the Coastal Commission actually requires for ADUs in the LA Coastal Zone — process, timeline, fees, and the design choices that make a CDP application sail through.