Ventura County · Timeline
How long an ADU really takes in Ventura County
Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.
Stage by stage
- Survey + design
- 3–5 — Standard suburban lots.
- City plan check
- 4–6 — Ministerial under state law.
- HOA review (where applicable)
- 4–8 — Conejo Valley HOAs add a layer.
- Construction
- 14–20 — Detached new-build on flat lot.
Permit clock vs total schedule
- Ministerial permit
- 6–10 weeks
- Discretionary review (when triggered)
- 14–24 weeks
What slips schedules in this area
- State ADU law sets the floor — every city in the county runs ministerial review under it.
- Coastal Zone parcels (Ventura, Oxnard waterfront) may add a CDP review.
- VHFHSZ on the foothills (Ventura backcountry, Conejo Valley north) → Chapter 7A assemblies.