How long an ADU really takes in Westside

Total elapsed schedule from the first site walk to the final inspection. Plan check is rarely the long pole — utility coordination and trade scheduling usually are.

Stage by stage

Survey + design
3–6 — Faster on flat parcels east of Lincoln.
Plan check (LADBS or SM B&S)
4–6 — Ministerial — no neighbor notice.
Permit issuance + utility coordination
1–2 — LADWP service drop is the long pole.
Construction
16–22 — Detached new-build, slab to final.

Permit clock vs total schedule

Ministerial permit
8–12 weeks
Discretionary review (when triggered)
16–28 weeks

What slips schedules in this area

  • Santa Monica and Venice have their own ADU ordinances on top of state law — both more permissive, not less.
  • Coastal Zone parcels (west of Lincoln) may need a CDP from the California Coastal Commission.
  • Soft-story retrofit ordinance (Santa Monica + LA) often gets paired with the ADU permit on older multifamily.
quote · westside

Quote for Westside timeline.

When are you trying to break ground? We'll lay out a realistic week-by-week schedule for your jurisdiction.

Phone or email — at least one so we can reply.

We tag this lead as la-westside · timeline so the right estimator picks it up. First site walk is free.

Call